Projects

Long-term containers for jobs, estimates, invoices, purchasing and documents.

Office Action Queue

5
TaskProject #Project NamePMCategoryDate Created
Mechanical rough inspection failed — inspector wants revised hanger spacing letter from the engineer. Office needs to request the letter.P-2041Harborview HQ — HVAC RetrofitJ. BlakePermit/Inspection06/28/2026
Third-floor split system is on a 6-week lead time. Need PO released this week to hold the schedule.P-2041Harborview HQ — HVAC RetrofitJ. BlakeMaterial/Ordering06/26/2026
Hit ledge in the north trench. Change order pricing needs to be sent to the GC for signature.P-2019Industrial Way Site PrepJ. BlakeAccess/Site Conditions06/24/2026
Utility disconnect window still unconfirmed — office to call Eversource scheduling desk.P-2036Marina Dr Electrical UpgradeR. PatelScheduling06/21/2026
Homeowner asked for a second egress light at the stair landing. Priced verbally at $480.P-2029Grove Ln Basement BuildoutK. OrtizCustomer Request06/19/2026
P-2004Beach Dr EV Charger BankGupta, AnikaPrimary SiteElectrical - New Construction/Remodel CommercialR. PatelIn Progress$88,60007/13/2026
P-2033Cedar St New ConstructionBlake Family TrustMain OfficePlumbing Construction ResidentialL. ChenIn Progress$612,00007/06/2026
P-2012Vista Way Radiant HeatKhan, AyeshaPrimary SiteHVAC Construction ResidentialM. AlvarezIn Progress$45,00005/04/2026
P-2038Ridge Rd Plumbing Rough-InBramble HomesMain OfficePlumbing Construction ResidentialM. AlvarezIn Progress$100,60004/20/2026
P-2041Harborview HQ — HVAC RetrofitHarborview Development LLCMain OfficeHVAC Construction CommercialJ. BlakeIn Progress$462,50004/12/2026
P-2036Marina Dr Electrical UpgradeOrtega Marina GroupMain OfficeElectrical - New Construction/Remodel CommercialR. PatelIn Progress$152,00004/01/2026
P-2029Grove Ln Basement BuildoutLopez, MiguelPrimary SiteElectrical - Residential New Construction/RemodelK. OrtizIn Progress$87,20003/16/2026
P-2019Industrial Way Site PrepHollister LLCMain OfficePlumbing Construction CommercialJ. BlakeIn Progress$1,060,50002/09/2026
P-2001Harbor St Renovation PackageIves, MarciaPrimary SitePlumbing Construction ResidentialL. ChenIn Progress$380,80002/02/2026
Rows per page
1–9 of 9
Pageof 1